Estimation: Why do we do it?

 

There are those who consider that estimating is impossible and a waste of time, a useless endeavor. There are those who believe it can be done, but only under certain conditions, and there are those who think that the secret lies in following a certain method... However, before discussing these points of view, I want to focus on a question often omitted in articles and books on estimation:

Why do we estimate? And I'm not talking about the theoretical reasons typically used in books on the subject, but rather, out there, in the real world. I don't want to generalize, so what I will say next is strictly based on my own experience.

We don't estimate to know how long the project will take; the client usually has already set a deadline that is unlikely to change.

Why do we estimate then? We estimate to see if we can do something within the time and budget that are already established and that sounds to the client like what they asked for (because if one thing is certain, it's that most clients don't really know what they want until they've seen a couple of progress demos).

The agile community tells us: don't estimate, do everything by time and materials, although in reality what it's saying is "don't estimate beyond the next sprint" and "lose any client who is only willing to buy projects at a fixed cost and time." It would be nice if the world were that easy, but the fact is that it's not: most of the clients I've encountered in the consulting world want a budget upfront... Those of us who would like everyone to understand Scrum sometimes find it absurd, a display of their ignorance some say, but let's put ourselves in their shoes: who, when taking their car to the shop, expects to be told: we're going to fix your car iteratively, give us your bank card with an open voucher and then check your balance to see how much it was at the end...

And yet we go to the doctor, and while each visit may have a fixed cost, we don't ask the doctor to give us the cost of the medicines before diagnosing us, nor do we force them to tell us the maximum number of consultations we'll need... Medical treatment is completely iterative... Maybe one day we'll recognize the similarities between curing the most sophisticated biological system we know and creating or composing new systems... In the meantime, let's think... Why are there fixed-cost projects that do work? The level of uncertainty clearly visible to the educated mind at the start of the project should guarantee that this never happens... What's different in those projects? Maybe it's not obvious, but in my experience, it's quite simple: the scope was better defined, either because the client themselves had already done some pre-analysis, or because the consulting team did the same... SACRILEGE! Am I daring to say that the correct way to carry out a project is with Waterfall?

NO! To believe that is to ignore the principle of diminishing returns: those who believe that this indicates Waterfall is the answer are making the mistake of thinking that if some analysis is better than none, then double or quadruple the analysis will bring a benefit directly proportional. Well, welcome to the real world: things don't work like that, if you do a lot of analysis, you also consume a lot of time and while your understanding of the situation becomes more precise, it also becomes progressively outdated... The world doesn't stop changing because you analyze a particular point of it in time and by the time you turn to compare your analysis with the current reality, the world has already changed: the conclusions of your analysis are now obsolete.

Zero analysis? Bad. Exhaustive analysis? Bad... What to do then? Find out how much is "enough" but first understand enough for what? Many books on estimation talk about achieving 75% accuracy, as the ultimate goal of a well-done estimate. In my experience, that perception is wrong. What good does it tell a client: to succeed in what you're asking, I need one million pesos, if the client only has (or claims to have) a third of that? It's no use, the client won't have their product, and we won't have our project. What to do then?

Look for the "as if," the first time I heard that phrase it seemed naive: do a one million project for a third? Impossible! But then it happened that some people asked me: why? And I complicated my life giving a thousand explanations about the complexities that are part of software development (many of which I didn't understand then... and many of which I still don't fully understand now) and... I couldn't convince them, and ended up trapped in horrendous Dead March projects from which I not only received pressure from the client, desperate because the project was nowhere near completion by the deadline, but also from the company I worked for, equally desperate as the project's margin eroded away...

And after finishing that project, we embarked on another just like it... How do we break that cycle? Is  it true, as I recently read on Twitter, that assuming is the mother of all problems in system development. I will talk about that in my next post...

 Originally published in Javamexico